Third Public Notice of the Completion Environmental Protection Acceptance for the Gas Extraction System Project at Shaft No. 3 of Duan’s Coal Mine, Qinhé Energy Group Co., Ltd.


Release Date:

2025-04-21

Duan’s Coal Mine, Qinhé Energy Group Co., Ltd. 3# Windshaft Gas Drainage System Project Located in Duanshi Town, Qinsui County, Jincheng City, Shanxi Province. New construction at Duanshi Coal Mine Shenjiazhuang Within the ventilation shaft site The environmental protection acceptance monitoring report for this project has now been completed. Following an on-site inspection by the acceptance team formed by our company, the project meets the acceptance criteria. In accordance with the Interim Measures for Environmental Protection Acceptance of Completed Construction Projects (National Environmental Protection Regulation No. …), [2017]4 In accordance with the requirements of Document No. ____, the complete version of the project’s completion acceptance monitoring report form is hereby made publicly available for a period of ____. 2025 year 4 month 21 Date to 2025 year 5 month 20 Day, lasting for 20 working days. Members of the public are welcome to review and exercise oversight.

Method for obtaining the complete version of the Environmental Protection Acceptance Monitoring Report for the project’s completion:

See the attachment.

 

Contact: Wang Xiangbin

Contact phone number: 18235655990

 

Duan’s Coal Mine, Qinhé Energy Group Co., Ltd.

2025 year 4 month 21 day