Qinhe Energy Group Co., Ltd. Yongan Coal Mine No.15 Coal Horizontal Extension Project Commencement Filing Announcement


2023-11-26

Qinhe Energy Group Co., Ltd. Yong'an Coal MineThe Construction Organization Design of No.15 Coal Horizontal Extension Project has been reviewed and approved by relevant units such as construction, design, supervision and construction, and has been approved by Qinhe Energy Group Co., Ltd., the main enterprise, and the construction of the project has been approved by Qinhe Fa [2023] No. 370. Qinhe Energy Group Co., Ltd. Yongan Coal Mine No. 15 coal horizontal deep project information announcement is as follows:

Project Name:Qinhe Energy Group Co., Ltd. Yong'an Coal MineNo.15 Coal Horizontal Extension Project

Construction site:Shanxi Province Jincheng City Qinshui County Jiaxing Town Yong'an Village

Construction scale:600000 tons/year

Construction content:Qinhe Energy Group Co., Ltd. Yong'an Coal MineHorizontal extension of No.15 coal

Project investment:660.7268 million yuan

Construction period:Total length of shaft works when the project is handed over to production13090m, construction period 36 months

 

hereby announce

Qinhe Energy Group Limited